[Case Study] Total Elimination of Waste Tofu | Food Processing Plant

CASE STUDY: Food Processing Plant (Tofu Manufacturing, Shiga Prefecture)

Total Elimination of High-Moisture Waste Tofu Left by Competitors’ Machines.
Eradicating Severe Odors and Pest Risks at the Source.

Equipment Installed: Commercial Food Waste Disposer GOMISER GH-35

Results: Successfully eliminated high-moisture “waste tofu" that competitors’ equipment failed to process.
Reduced the severe odor and pest risks associated with industrial waste storage to absolute zero.
Results: Total elimination of waste tofu, eradicating storage odors and pests.

Image of GOMISER commercial food waste disposer installed at a tofu manufacturing plant in Shiga Prefecture

(*Image for illustrative purposes only)

[A Facility Dedicated to Advanced Hygiene Management]

Food Processing Plant (Tofu Manufacturer)

Location: Shiga Prefecture
This facility specializes in the manufacturing and processing of tofu. They faced a significant challenge in managing large volumes of food loss and manufacturing residue—particularly high-moisture, off-spec “waste tofu"—inevitably generated during their daily operations.
In food processing plants requiring strict hygiene management based on HACCP and other standards, processing these high-moisture residues quickly and cleanly is the foundation of safe and reliable production. This plant opted for the highly logical approach of “immediate elimination at the source," ensuring waste never lingers on the factory floor, thereby maintaining a pristine manufacturing environment.

■ Pre-Installation Challenges: The Barrier of High-Moisture Residue and the Limits of Hygienic Storage

[Site Characteristics] High-moisture waste tofu decomposes extraordinarily fast. Storing it long-term as industrial waste within a food processing plant inevitably creates a breeding ground for severe odors and pest infestations.

Previously, to resolve their food waste issues, this plant had conducted practical tests with a competitor’s waste elimination machine. However, the machine’s decomposition capacity could not keep up with the specific moisture content and composition of waste tofu. They were forced to abandon the installation simply because the machine “could not fully process the load."
As a result, they had no choice but to continue storing the waste inside the plant until industrial waste collectors arrived. The odors and pests generated during this waiting period became a massive source of stress and a major compliance concern for employees committed to maintaining strict hygiene standards.

⚠️ Key Challenges at the Time

  • Concerns from Competitor Tests: Insufficient processing capacity for high-moisture waste tofu forced them to abandon previous solutions.
  • Increased Storage Risks: Severe odors and pest generation caused by retaining industrial waste inside the plant before collection.
  • Hygiene Management Concerns: A lack of a fundamental solution to consistently maintain the pristine environment required of a food processing facility.

■ Reason for Selection: Reliable Verification Through Sample Testing and a 1-Month Demo

Given their past experience with competitors’ machines failing to process their waste, the client was understandably cautious. Therefore, rather than pushing for an immediate sale, we proposed a “phased verification process."
First, we asked the client to send us samples of their actual waste for preliminary “processing tests." Following this, we deployed a demo unit to the actual factory floor for one month. This allowed employees to rigorously verify its processing capabilities within their standard daily workflow.
Ultimately, it was proven on-site that GOMISER’s powerful, specialized microorganisms could smoothly decompose waste tofu into water. The ability to “confirm the actual capabilities in advance" became the deciding factor, leading to the official installation of the GH-35 model.

■ Installation & Results: Freedom from Storage Stress and a Cleaner Manufacturing Floor

Installation view of the GOMISER GH-35 commercial food waste disposer at a food factory in Shiga Prefecture

(Photo: The GOMISER GH-35 installed in the food processing plant)

With the introduction of GOMISER, manufacturing residues like waste tofu can now be deposited and eliminated immediately on-site as they are generated.
This completely eliminated their most pressing challenge—"long-term storage until industrial waste collection day"—and entirely resolved the severe odors and pest infestations that had plagued the plant. The client reported, “We are incredibly glad we could confirm the results with a processing test prior to installation. The odors and pests we were so worried about are completely gone, and we are highly satisfied," expressing strong confidence in the results.

  • ✅ Eradication of Odors and Pests: Eliminating waste before decomposition starts removes hygiene risks at their root.
  • ✅ No More Storage Space Needed: Eliminating the need to retain industrial waste keeps the backroom impeccably clean.
  • ✅ Guaranteed ROI Before Purchase: Rigorous verification using a demo unit ensured a reliable and confident capital investment.

■ AIC Commentary: Expert Insights

In food processing plants, completely decomposing high-moisture food residues (such as waste tofu) with a disposal machine presents technical hurdles that are difficult to evaluate based on catalog specifications alone. As seen in this case study, many companies nearly give up on implementation after testing competitors’ products that ultimately fail to process the load.

[Professional Know-How] Securing “Reliable Capital Investments" in Food Processing Plants

  • ✓ The Importance of “Sample Testing" and “Demo Units":
    Waste composition, moisture content, and operational workflows vary drastically from plant to plant. Before finalizing any sale, we prioritize a process that involves processing tests using the client’s actual waste and providing on-site demo units. This ensures that employees gain the hands-on confidence and proof that the system will function flawlessly in their specific environment.
  • ✓ “Odor and Pest Control" as a Prerequisite for HACCP:
    GOMISER goes far beyond simply reducing industrial waste disposal costs. By enabling immediate processing at the source, it dramatically elevates the plant’s hygiene standards (pest and odor control), serving as a powerful foundational asset for HACCP compliance.

Plant managers who are wondering, “Can our unique waste really be decomposed?" or who have experienced failures with competitors’ machines in the past, are strongly encouraged to utilize our preliminary processing verification and demo unit loan services.

Client Feedback & FAQ

Having previously abandoned an installation after a competitor’s elimination-type machine failed during testing, our main concern was whether the system could truly decompose highly moist waste like waste tofu.

We had to store the waste inside the plant until the industrial waste contractor picked it up. The severe odors and insect infestations generated during that storage period were a massive issue for our hygiene management.

The deciding factor was the ability to confirm its processing capabilities with our own eyes in our actual factory. This was achieved by sending our actual waste for preliminary testing and then having a demo unit on-site for a month prior to implementation.

We are extremely satisfied. Because we no longer need to store waste, the odors and pests that had constantly worried us have completely disappeared, allowing us to maintain a pristine manufacturing environment.

Commercial Food Waste Disposer GOMISER GH-35

Installed Model

Commercial Food Waste Disposer “GOMISER" GH-35

The optimal standard model for mid-sized facilities generating tens of kilograms of food waste daily. Its powerful proprietary microorganisms effortlessly decompose even high-moisture residues like waste tofu, ensuring a pristine manufacturing environment completely free from storage odors and pests.

▶ View Product Details & Specifications

Biodigester Consultations, Free Estimates, and Brochure Requests

Professional Support to Achieve
Environmental Improvement & Cost Reduction

We propose the optimal models and installation plans tailored to your specific facility conditions.
Please feel free to ask about “Site Visits" or “Trial Monitor Installations."

Simulate the Installation Effects for Your Company for Free

Find out your "cost reduction" and "CO2 reduction" instantly based on your current data.

Cost Reduction Simulator
Cost Reduction & Management
How much can you save
compared to your current costs?
Try Cost Reduction Simulator 👉
Food Waste CO2 Reduction Simulator
SDGs & ESG Measures (Scope 3)
Check your CO2 reduction and
SDG contribution level!